Project
2nd, 7th & 10th Floor, Blue Fin Building, 110 Southward, SE1 0SU
Client
Oxford Properties
Project Team
Client | Oxford Properties Group, Project Manager, Cost Consultant and Building Engineering Services Designer | Cushman & Wakefield, Architect | Barr Gazetas, Designer | IDL, M&E Engineer | IM Mechanical and Electrical Services Ltd
Value
£3.5m
Procurement Route
Single stage
Area
40,000 sq ft
Duration
17 weeks
Sector
Real Estate
Work Type
Cat A
Parkeray delivered a 40,000 sq ft Cat A fit out across three floors of the Blue Fin Building for Oxford Properties, revitalising key areas, including the external terrace, and preparing the space for future occupation in a live, operational environment.
Key Features
Delivery Highlights
Ryan Wager
Project Director
David Sweeney
Project Manager
Michaela Maloney
Assistant Project Manager
Ryan Hignell
Commercial Director
Miru Zelalem
Commercial Manager
Rod Alves
Commercial Manager
Amelia Marshall
Assistant Commercial Manager
Thomas Simpson
Assistant Commercial Manager
Robert Cafferty
Services Director
Chris White
Services Manager
Lizzie Fisher
Assistant Services Manager
Bruce Pounder
Head of Design Management